July 17, 2014 by Lynn Winterboer Leave a Comment

What is the Role of a BI Analyst in an Agile Project?

How an agile BI Analyst collaborates with the Product Owner and fits into an Agile Team

Below are some questions that came in from a recent webinar my friend, Hubert Smits, and I gave on Acceptance Criteria for Business Intelligence User Stories.

Q: What is the role of a Business System Analyst in Agile?

A: Analysis is an important skill to have on any agile BI team. Business analysis provides detailed insight into the organization’s needs, the calculations and transformations required to meet the needs, and how the users will most benefit from the new feature being developed.  Systems analysis digs into the source systems to find the right data required to fulfill the business needs, and figure out how to best acquire that data into the DW/BI system.  Data analysis provides data quality and integration information that guides some of the most challenging aspects of BI development.

Whether the people exercising these skills have the titles of “BI Analyst” or “Developer” or “Tester” doesn’t matter at all in an agile project.  What is important is that these skills are applied toward completed user stories.  While the people with “Analyst” in their titles are usually the most productive in these skills, there are others in the team who could learn to be effective analysts in order to keep the work flowing.  I’d rather have a developer jump in and do data quality analysis that needs to be done, rather than sitting idle waiting for a development task to be ready for development skills… just as a Business Systems Analyst could help out with testing if that’s the current task needing more hands-on-deck to keep the work moving forward.

__________________________________________________________

Q: “Should a Business Analyst collaborate with the Product Owner?”

A: Absolutely!  Often in BI teams, the Product Owner is juggling relationships with a multitude of organizational departments and won’t have the bandwidth do detailed business, systems, or data analysis on every user story, even to get a story to the point of “ready” for the team to work on it. Many experienced analysts end up in the role of Product Owner, which requires not only their existing analysis skills, but also additional leadership, prioritization, and facilitation skills.  It’s a lot for a single person to take on, and additional help is always required in order for the team to be working on the right things at the right times. Once the team has started working on a story, people doing analysis work on that story will have lots of questions for the PO and other people the PO will bring into the conversation.  Collaboration is required in this key relationship!

__________________________________________________________

Q: How does each role relate to each other and what should be the Business Analyst position vis a vis the entire Agile team?

A: In a healthy agile team, people have skills and desires to learn skills, and don’t focus on titles and roles. The team should be small enough (5 – 9 people) so that you don’t need a title to understand what a person can do to help create working BI features. I mention this because I see lots of teams trying to do “mini waterfalls” in 2-week sprints by having people strictly retain the roles they had in a traditional BI project structure, and then they get frustrated that they aren’t seeing the speed and quality they expected with a change to an agile approach.

Having said that, on a tactical level anyone doing analysis on an agile BI team is a member of the delivery team… as are the people who do data modeling, ETL development, metadata development, report building, testing, etc. That whole group of people works together to deliver working functionality in a short amount of time.  In scrum, there are only 3 official roles: Product Owner (person who identifies and prioritizes the work to be done), Team Member (all the people who do the work to deliver working BI features), and Scrum Master (the person who “holds the process” to keep things moving smoothly so the team members can deliver results as quickly as possible). Therefore, an Analyst is a Team Member and is not separate from the team.

I often hear similar questions, and often the “right” answer for the person asking depends on their organizational constraints and specific situation.  If you would like some help figuring out how business analysts on your BI team “fit” into an agile approach, I’d be happy to have a more targeted conversation!


 

Hear the webinar in its entirety: Acceptance Criteria

Share Your Questions & Comments!

Filed Under: Blogs, Cutter Tagged With: Business Analysts, Collaboration, Cross-Functional Skills, Data Analysts, Definition of Ready, Multiple Business Domains

November 15, 2013 by Lynn Winterboer 1 Comment

Do Less by Committing to More

By Ken Collier and Lynn Winterboer (first published in TDWI BI This Week on July 30, 2013)

Agile leaders focus more on the continuous delivery of high-priority value to business stakeholders and less on making sure each worker is always busy. We explain how your BI program will benefit by limiting developer multi-tasking.

Ben and Susan are each a DW/BI director at their respective companies; each leads a department of roughly the same size. Both have the staffing necessary to organize three dedicated, cross-functional teams. Ben’s department is organized into dedicated teams while Susan has functional skills “pools” from which project teams are staffed. Both directors are planning for the coming year and have a similar set of 12 projects to schedule.

Through collaboration with business stakeholders, product owners, project managers, and the program management office (PMO), Ben has a prioritized backlog of funded project requests to schedule into the calendar. With help from technical leaders, he has completed some high-level project sizing and assigned durations of two, three, or four months per project. Projects longer than four months are divided into multiple phases, each designed to fit into one of these smaller time periods. This ensures that long-running projects do not block other projects by dominating the department’s capacity.

Ben assigns a dedicated team to each of the first three projects in the backlog. He then estimates when each team might be free to start its next project, continuing in this manner until he has a reasonable program plan for the coming year:

Collier Winterboer Agile Graph 1

Because Ben continuously pulls from a program backlog, the whole process takes less than an hour of Ben’s time, and he is comfortable sharing this project road map with stakeholders and the PMO. This company’s agile culture includes an agreement that once a project is started, the team will stay focused on that project until the project time frame is finished. Adaptation to project reprioritization does not affect projects that are already underway. Because business and management stakeholders are involved in the prioritization process, there are no surprises about the program schedule. Everyone also understands that the program backlog is always evolving based on the changing needs of the business.

Meanwhile, Susan is also doing resource planning for her department. She has met with each of the BI team’s key stakeholders to get their input on priorities for the year. She’s heard passionate explanations from each about why their top priority projects are important to the company, such as “I need sales pipeline analytics ASAP so I can ensure the marketing team is ready to support our key industries!” (from the VP of sales and marketing) and “I need net profit margin per product so I can report accurately to our investors!” (from the VP of finance).

Susan understands the importance of each of these projects, and wants to get them started as quickly as possible. Moreover, her CIO is focused on maximizing personnel utilization, desiring that every team member be utilized 100 percent on project work. Susan believes if she gets team members started on more projects sooner, and has them spread across multiple projects, her CIO and stakeholders will be confident she’s doing everything she can to focus her teams appropriately. Therefore, she structures each project to have a dedicated core team of two developers with the part-time support of product owners, project managers, data modelers, testers, and business analysts. Several of these projects are expected to take 6-12 months to complete, so Susan needs to run at least six projects concurrently in order to meet the urgent needs of the business.

Winterboer Collier Agile Project Graph

As Susan’s delivery strategy gets underway project team members plan in two-week iterations for the multiple projects to which they are assigned. This means that each team member is attending at least two, and sometimes three, planning meetings every two weeks. They are also attending multiple daily stand-up meetings, iteration showcases, and retrospectives. Project managers and product owners are only able to devote cursory time to assist on each project, and they often feel disconnected from what’s actually happening. The core developers dedicated to each project are frustrated because they cannot count on having the support they need from data modelers, testers, business analysts, and others. This is further complicated by the fact that there doesn’t seem to be any common time when the entire project team can work together.

Every team seems to over-commit on each iteration, failing to finish stories as planned. In part this is caused by the significant overhead incurred as team members switch from one project context to another (approximately 20 percent per additional project, per Weinberg, 1991).

Susan failed to account for this waste in her resource plan. This triggers two side effects. It is evident that the projects will not finish on time, and teams’ (and Susan’s) ability to accurately predict when each will finish is nebulous. Each team is cutting testing corners under the duress of over commitments, which will cause increased maintenance/support issues.

As much as Susan tries to create a great culture and work atmosphere, people in her department are unhappy. They are stressed by the job pressures and often feel like hamsters on a wheel, running fast and getting nowhere. There is a general lack of collegiality in the BI group and people often blame their colleagues when things go badly. Many staff members have remarked on the difficulty of trying to do too many things at once, but Susan doesn’t think they understand the pressure she is under to meet the needs of the business.

Consider the differences in the directors’ situations.

  Ben  Susan
Project focus Finishing projects as soon as possible Starting as many projects as possible
Staffing philosophy Prioritize project delivery over staff utilization Prioritize staff utilization over project delivery
Corporate prioritization PMO facilitates cross-functional prioritization for the BI team so the BI director is not left with making these important decisions him/herself BI director makes cross-functional prioritization decisions
Corporate culture Supports a team staying focused on a single project until it is complete Team splits focus across multiple projects at a time
Stakeholder expectations Stakeholders understand the relatively short timeframe when they need to be available for each project to be successful Stakeholders must be available for long periods of time if they want their projects to be successful
Project completion Project focus is constrained; each successive project starts later but is completed earlier Project focus is stretched; each project starts as early as possible and is completed much later
BI director’s confidence Confident enough to get started on project work, knowing he’s done the right amount of planning at this point. Glad it only took him an hour! Expects several easy re-planning sessions throughout the year due to changing corporate priorities. Worn out after an entire afternoon spent wrestling with a spreadsheet and resource allocations. Hopes she didn’t miss anything in the details. Uncomfortable with the message she will take to the CIO and stakeholders, not to mention the impacts of stress on her team. Expects several painful re-planning sessions throughout the year due to changing corporate priorities.

Big Themes

It is often counter intuitive that dedicating a team to one project at a time will better satisfy stakeholders, yet agile teams that focus exclusively on one thing at a time are able to deliver value more quickly to their organizations because:

  • Starting projects earlier does not ensure they will be finished sooner
  • Project multi-tasking has an unseen penalty cost that will further delay finish dates
  • Focusing on maximizing utilization over project completion has unintended consequences

Resources

Brown, R. (2010, June 29). Multitasking Gets You There Later. Retrieved June 20, 2013, from InfoQ
Cohn, M. (2009). Succeeding With Agile. Boston: Addison-Wesley Professional.
Weinberg, G. M. (1991). Quality Software Management Volume 1: Systems Thinking. Dorset House.

Filed Under: Articles, TDWI Tagged With: Business Value, Cross-Functional Skills, Ken Collier, Leadership, Program Management, Roadmap

Search This Website

SiteLock

Events

  • Lynn Hosts: Agile Denver DW/BI March Meetup Mar 23, 2017
  • Agile Denver March Meetup Mar 27, 2017
  • Agile Games and Mob Programming 2017 Conferences Apr 03, 2017

About Us

Winterboer Agile Analytics provides training, coaching and consulting for data warehousing and business intelligence. We are located in Denver, CO.
Contact Us

© 2017 · www.WinterboerAgileAnalytics.com · Created and Managed Starkweather Marketing, LLC